OPERATING PROCEDURE
<Model 20~100>
1. Remove the service panel and filter with the pro-
cedure explained in section 8-1.
2. Removing the control box cover (Fig.2-1).
• Remove the fixing screws (one) of the control box
cover (A), and remove the cover.
* At this stage, the following servicing is possible.
1 Operation and check of the switches (listed below)
which are on the address board.
•
Rotary switches SW11, 12
Address setting
•
Rotary switch SW14
Branch port setting
• Dip switch SW1 Function change 1
• Dip switch SW2 Capacity setting
• Dip switch SW3 Function change 2
• Dip switch SW4 Model setting
• Dip switch SW5 Option setting
• Dip switch SW6 Model change
• Dip switch SW7 Function change 3
2 Connection check and local connection of lead
wires (listed below) which are connected to the
control box (B).
•
Power supply lead wire (Connected at the factory)
• Drain pump lead wire (Connected at the factory)
• LEV lead wire (Connected at the factory)
• Panel vane motor lead wire (Connected locally)
• Panel limit switch lead wire (Connected locally)
• Drain pump trial operation connector
(Connected locally)
•
M-NET transmission lead wire (Connected at the factory)
• MA remote controller transmission wire
(Connected at the factory)
• Fan motor lead wire (Connected at the factory)
• I
ntake air sensor lead wire (Connected at the factory)
•
Fluid piping sensor lead wire (Connected at the factory)
•
Gas piping sensor lead wire (Connected at the factory)
(• Humidifier lead wire)
(• Auxiliary electric heater lead wire)
3 Control board exchange
4 Condenser exchange
5 Power supply transformer exchange
6 Intake air sensor exchange
Note: The control PCB, capacitor and power trans-
former could fall off when removed.