22
OPERATING PROCEDURE
<Model 125>
1. Remove the service panel and filter with the pro-
cedure explained in section 8-1.
2. Removing the connector cover (A).
• Remove the fixing screws (two) of the connector
cover (A), and remove the cover. (Fig.2-2)
* At this stage, the following servicing is possible. (It
is even possible with the filter attached.)
1 Operation and check of the switches (listed below)
which are on the address board (B).
•
Rotary switches SW11, 12
Address setting
•
Rotary switch SW14
Branch port setting
• Dip switch SW1 Function change (main)
• Slide switches SWA, C Airflow rate change
2 Connection check and local connection of lead
wires (listed below) which are connected to the
control box (C).
•
Power supply lead wire (Connected at the factory)
•
Drain pump lead wire (Connected at the factory)
•
LEV lead wire (Connected at the factory)
•
Panel vane motor lead wire (Connected locally)
•
Panel limit switch lead wire (Connected locally)
•
Drain pump trial operation connector (Connected
locally)
3. Removing the control box (C)
(1) Remove the fixing screws (three) of the filter fixed
plate (D). (Fig.2-3)
(2) Also remove the fixing screws (three) of the con-
trol box cover (F) and remove it. (Fig.2-4)
* At this stage, the following servicing is possible.
1 Operation and check of the switches (listed below)
which are on the control board.
• Dip switch SW2 Capacity code setting
• Dip switch SW3 Function change (auxiliary)
• Dip switch SW4 Model code setting
And the address board exchange.
2 Connection check of the lead wires (listed below)
which are connected to the control box
•
Power supply lead wire
• Remote control communication lead wire
•
Fan motor lead wire
•
LEV lead wire
•
Drain pump lead wire
•
Drain sensor lead wire
•
Intake air sensor lead wire
•
Liquid piping sensor lead wire
•
Gas piping sensor lead wire
•
Power supply transformer lead wire
•
Address board lead wire
•
Panel vane motor lead wire
•
Panel limit switch lead wire
(Fig.2-2)
PHOTOS&ILLUSTRATIONS